TradeAdvisor®

Harbour Plumbing

Gantt

J-1808

Reroute bathroom waste

Naledi Petersen · 14 Balfour Road, Rondebosch

Open the site in maps

Progress

55%

On the job

Lerato, Pieter

Revised incl VAT

R7 136.90

2 variations

2026-10-16

Plan end

2026-10-17

Forecast

+1d

Variance

Plan Forecast Late

Current phase: Fit and test · 45%

4 tasks behind the locked plan.

Task
10111213141516171819
  • Attend and isolate

    Lerato Molefe · 100%

  • Strip and prepare

    Lerato Molefe · 100% · +1d

  • Fit and test

    Lerato Molefe · 45% · +2d

  • VO-001Fit isolation valves

    Pieter van Wyk · 0%

  • Compliance certificate

    Amina Jacobs · Milestone · +2d

  • Handover

    Lerato Molefe · Milestone · +1d

Grey is the locked plan. Colour is actual or forecast. Amber means the finish is later than the plan.

Upcoming: Compliance certificate (2026-10-15) · Handover (2026-10-16)

Variation orders

Original contract plus approved variations.

Original R4 956.00 · Approved VOs R1 250.00 · Revised R6 206.00 ex VAT · R7 136.90 incl VAT

  • VO-001 · Fit isolation valves · approved

    R1 250.00 ex VAT · 1 day

  • VO-002 · Move the gully · sent

    R1 860.00 ex VAT · 2 days

Notes and checklist

Photos, time, materials

300 minutes on this job. Current phase Fit and test.

  • 6 × 50mm waste pipe