Harbour Plumbing
J-1808
Reroute bathroom waste
Naledi Petersen · 14 Balfour Road, Rondebosch
Open the site in mapsProgress
55%
On the job
Lerato, Pieter
Revised incl VAT
R7 136.90
2 variations
2026-10-16
Plan end
2026-10-17
Forecast
+1d
Variance
Plan Forecast Late
Current phase: Fit and test · 45%
4 tasks behind the locked plan.
Grey is the locked plan. Colour is actual or forecast. Amber means the finish is later than the plan.
Upcoming: Compliance certificate (2026-10-15) · Handover (2026-10-16)
Variation orders
Original contract plus approved variations.
Original R4 956.00 · Approved VOs R1 250.00 · Revised R6 206.00 ex VAT · R7 136.90 incl VAT
VO-001 · Fit isolation valves · approved
R1 250.00 ex VAT · 1 day
VO-002 · Move the gully · sent
R1 860.00 ex VAT · 2 days
Notes and checklist
Photos, time, materials
300 minutes on this job. Current phase Fit and test.
- 6 × 50mm waste pipe